Various Projects

Hyundai Engineering & Construction Co . LTD

Project: Repowering of Jebel Ali Power & Desalination “D”, Phase 2.
Scope of Work: Insulation works
Area : Dubai                   Year: 2001

Project: Repowering of jebel Ali Power & Desalination “D”, Phase 2.
Scope of Work: Insulation work of turbine & boiler in unit 1,2 &3
Area : Dubai                   Year: 2002

Project: South Pars Field Development Phase 4 & 5 , Assaluyeh.
Scope of Work: Supply and application of the hot, cold & acoustic insulation system for onshore and offshore facilities.
Area : Iran                   Year: 2005

Project: South Pars Field Development Phase 4 & 5 , Assaluyeh.
Scope of Work: Insulation and scaffolding.
Area : Iran                   Year: 2005

Nasser S. Al Hajri Corp.

Project: Al Fasel PDH Project.
Scope of Work: For supply and application of Insulation Works
Area : KSA                   Year: 2009

National Petroleum Construction - Abu Dabhi

Project: ZADCO- Zirku Gas Project.
Scope of Work: Hot Insulation Works
Area : Abu Dabhi                   Year: 1998

Saipem

Project: OLT Livorno – FSRU Project.
Scope of Work: FireProofing work , 3 nos Domes, Supports of regasification module.
Area : Dubai                   Year: 1998

ALSTOM Power Italia S.P.A

Project: Al Hidd Power & Water Facility, Bahrain.
Scope of Work: Insulations, painting and scaffolding work.
Area : Bahrain                   Year: 1999

Project: Shoaiba Power Plant – Phase 1 and Phase 2.
Scope of Work: Insulation, refractory and scaffolding works.
Area : KSA                   Year: 2003

Project: Al Hidd Power & Water Facility Phase 2, Bahrain.
Scope of Work: Insulation, painting and scaffolding.
Area : Bahrain                   Year: 2003

Project: Alba PS4 Combined Cycle Project.
Scope of Work: Insulation & painting works.
Area : Bahrain                   Year: 2005

Project: Shaoiba Power Plant, Stage 1, Phase 1 & 2.
Scope of Work: Insulation, lagging and refractory works on the power plant.
Area : KSA                   Year: 2005

Project: Shaoiba Steam Power Plant Stage 1& 2.
Scope of Work: Thermal and acoustic insulation works.
Area : KSA                   Year: 2008

Project: Shaoiba Power Plant, Stage 1, Phase 1 & 2.
Scope of Work: Insulation, lagging and refractory works on the bolier.
Area : KSA                   Year: 2009

Abu Dhabi Gas Industries LTF (GASCO)

Project: Upgrading Refractory Lining.
Scope of Work: Upgrading the lining of the sulphur reaction furnace.
Area : Abu Dabhi                   Year: 2002

GS Engineering Abu Dhabi

Project: Green Diesel Project -Ruwais for Takreer Refinery.
Scope of Work: Painting ,scaffolding ,Insulation work.
Area : Abu Dabhi                   Year: 2011

Total South Pars

Project: South Pars Phase 2 & 3.
Scope of Work: Operation and maintenance, start-up & commissioning assiatnce, main contractor for offshore and on shore rigging services. Main contractor for painting and insulation services. Mian contractor for scaffolding services.
Area : Iran                   Year: 2003

Al Hasoun Sejong Electro-Mechanical EST.

Project: Umm Al Nar 1550MW Independent Water & Power Plant Project.
Scope of Work: Insulation works.
Area : Abu Dabhi                   Year: 2004

Lahoud Engineering Co. LTD.

Project: Al Hidd Power & Water Station, Phase 2.
Scope of Work: Insulation, painting & scaffolding works.
Area : Bahrain                   Year: 2003

Project: Alba Line 5 expansion – Power Station 4.
Scope of Work: Insulation, painting works.
Area : Bahrain                   Year: 2005

J.Ray McDermott Middle East, Inc.

Project: QATARGAS 3RD LNG train – Upstream Develoipment Project.
Scope of Work: Installation of passive fireproofing system.
Area : Abu Dabhi                   Year: 1999

Project: Ras Laffan Offshore Facilities Platform Project.
Scope of Work: Insulation works for the offshore facilities.
Area : Abu Dabhi                   Year: 1999

Project: Ras Laffan Offshore Expansion Project.
Scope of Work: Fireproofing work on structural steel equipment saddle, blast wall.
Area : Abu Dabhi                   Year: 2003

Project: Total Fina Elf Amenam Kpono Project – AMP1.
Scope of Work: Fireproofing of structures, beams and columns.
Area : Abu Dabhi                   Year: 2005

Al Habtoor Murray & Roberts.

Project: New Headquaters for ADNOC Group of Companies.
Scope of Work: Cementitous fireproofing of structural steel work.
Area : Abu Dabhi                   Year:

DOOSAN Heavy Industries & Construction

Project: AL Taweelah A2 Power & Desalination.
Scope of Work: Insulation work – subcontractor.
Area : Abu Dabhi                   Year: 2001 

Project: Umm Al Nar Desalination ‘B’
Scope of Work: Insulation work – subcontractor.
Area : Abu Dabhi                   Year: 2002

Project: Umm Al Nar Desalination ‘B’ – Boiler -11
Scope of Work: Refractory mixing and application – subcontractor.
Area : Abu Dabhi                   Year: 2003

Project: Umm Al Nar Desalination ‘B’ – Boiler -13
Scope of Work: Refractory mixing and application – subcontractor.
Area : Abu Dabhi                   Year: 2003

Project: Umm Al Nar Desalination ‘B’ – Boiler -14
Scope of Work: Refractory mixing and application – subcontractor.
Area : Abu Dabhi                   Year: 2003

Project: Umm Al Nar Desalination ‘B’ – Boiler -15
Scope of Work: Refractory mixing and application – subcontractor.
Area : Abu Dabhi                   Year: 2003

Project: 4 HRSG, Al Ezzel Power.
Scope of Work: Insulation work (piping of small and large bore – subcontractor.
Area : Abu Dabhi                   Year: 2007

Project: Tawaeelah New B Extension Project.
Scope of Work: Insulation & scaffolding works.
Area : Abu Dabhi                   Year: 2008

Nasser S. Al Hajri Corp.

Project: Mina Al Ahmad (MAA) Refinery, Contract No.NSH/MAA/65/2016
Scope of Work: Insulation, Mechanical and Technical works, Piping & Firproofing.
Area : Kuwait                   Year: 2018

DOOSAN Heavy Industries & Construction

Project: Doha Project, SWRO stage 1, Contract no – MEW/C/5099-2016/2017
Scope of Work: GRP Lamination, Insulation, Civil, Mechanical, Electrical works & Visa services.
Area : Kuwait                   Year: 2017 – Till date

PACADAR

Project: Kuwait Airport Terminal 2 project.
Scope of Work: Steel works – Steel reinforcement, pre-casting, rebar & steel fixing.
Area : Kuwait                   Year: 2019 – Till date

Zener Fire and Safety

Project: Doha Project, SWRO stage 1.
Scope of Work: Fire & Saftey Management.
Area : Kuwait                   Year: 2018 – 2019